Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring &
Audit Report
- June 2017 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
July 2017 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3
status of regulatory compliance..
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance.
6.4 Summary of action taken in the event of
and follow-up on non-compliance.
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.1 Summary
of the current status on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real
Time Noise Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air
Quality Monitoring Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15 (NOT USED)
Table 8.2 Summary of Environmental
Inspections for Contract no. HY/2009/18 (NOT USED)
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table
8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08) (NOT USED)
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
·
Rectification works for cracks/joints with water leakage inside OHVD
cells was completed.
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 1
base slab
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 2
base slab
·
Backfilling works
·
Cleaning of cross road duct
·
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
·
Outstanding works inside tunnel.
·
Concreting for roadside barrier
·
Erection of scaffolding for construction of top slab
·
Tunnel top slab
·
Dismantling of scaffolding.
·
Trial pit works for sewage works at Wan Shing Street
·
Rectification works for uneven road surface at Hung Hing Road
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street modification works
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of Slip Road 1
·
Construction of drainage
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at CMA1b was
rescheduled from 08 June 2017 and 14 June 2017 to 14 June 2017 and 15 June 2017
respectively;
The 24hr TSP monitoring at CMA5b was
rescheduled from 14 June 2017 to 15 June 2017;
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Reprovisioned Salt Water Pumping Station
·
Removal works of the existing sheet piles at the north face of WSD Salt
Water Pumping Station
·
Reprovisioned Wan Chai Ferry Pier;
·
Rectification works for the defects for the end of maintenance period of
Observation Deck and Staircase ST-01.
·
Rectification works for cracks/joints with water leakage inside OHVD
cells
·
Formwork, rebar fixing and concreting of HHR Flyover Approach Ramp.
·
Remedial works of tunnel wall, base slab and OHVD inside tunnel.
·
Remedial works for cross road ducts inside tunnel.
·
General cleaning and rectification works of OHVD, tunnel base slab, carrier
drain, cross road duct and manhole gully.
·
Rebar fixing and concreting of top slab.
·
Dismantling of scaffolding.
·
Crack mapping and remedial works to the tunnel structure.
·
Installation of waterproofing membranes at top slab.
·
Screeding for waterproofing membranes.
·
Commencement of king post load transfer.
·
Backfilling
·
Sewage Works at Hung Hing Road and Wan Shing Street
·
Trial pit at Hung Hing Road for sewage works.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
·
Re-surfacing work at Hung Hing Road
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction
·
Bridge E Permanent Parapet Construction at TB
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street modification works
·
Oil Street drainage works
·
Installation of skin parapet on TB bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of Slip Road 1
·
Construction of drainage
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and
Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental
Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D during the period 27 May 2017 to 26 June 2017.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all
exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
·
Associated road lighting, road signing, traffic control and surveillance
system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield
Depot – Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912
3328 |
|
Chun Wo – Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2587
1878 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Environmental
Officer |
Mr.
Terry Tsang |
6683
9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570
8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Site Agent |
Mr. David Lau |
3758 8879 |
|||
Deputy Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973
0803 |
|
Environmental Officer |
Mr. Chris Chan |
3973
0885 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. Rex Lau |
3557
6405 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6347 |
|||
China State- Build King JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Chris
Leung |
9210
7116 |
2566
8061 |
Site
Agent |
Mr. Thomas
Lui |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Environmental
Supervisor |
Mr. Desmond
Ho |
3557
6465 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Mr.
Malcolm Leung |
3973 0850 |
|||
Environmental
Supervisor |
Ms. Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
·
Rectification works for cracks/joints with water leakage inside OHVD
cells was completed.
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 1
base slab
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 2
base slab
·
Backfilling works
·
Cleaning of cross road duct
·
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
·
Outstanding works inside tunnel.
·
Concreting for roadside barrier
·
Erection of scaffolding for construction of top slab
·
Tunnel top slab
·
Dismantling of scaffolding.
·
Trial pit works for sewage works at Wan Shing Street
·
Rectification works for uneven road surface at Hung Hing Road
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street modification works
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of Slip Road 1
·
Construction of drainage
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Reprovisioned Salt Water Pumping Station
·
Removal works of the existing sheet piles at the north face of WSD Salt
Water Pumping Station
·
Reprovisioned Wan Chai Ferry Pier;
·
Rectification works for the defects for the end of maintenance period of
Observation Deck and Staircase ST-01.
·
Rectification works for cracks/joints with water leakage inside OHVD
cells
·
Formwork, rebar fixing and concreting of HHR Flyover Approach Ramp.
·
Remedial works of tunnel wall, base slab and OHVD inside tunnel.
·
Remedial works for cross road ducts inside tunnel.
·
General cleaning and rectification works of OHVD, tunnel base slab,
carrier drain, cross road duct and manhole gully.
·
Rebar fixing and concreting of top slab.
·
Dismantling of scaffolding.
·
Crack mapping and remedial works to the tunnel structure.
·
Installation of waterproofing membranes at top slab.
·
Screeding for waterproofing membranes.
·
Commencement of king post load transfer.
·
Backfilling.
·
Sewage Works at Hung Hing Road and Wan Shing Street
·
Trial pit at Hung Hing Road for sewage works.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
·
Re-surfacing work at Hung Hing Road
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction
·
Bridge E Permanent Parapet Construction at TB
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street modification works
·
Oil Street drainage works
·
Installation of skin parapet on TB bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Grouting
·
Construction of Slip Road 1
·
Construction of drainage
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS1241-16 |
12 Dec 2016 |
15 Dec 2016 to 06 Jun 2017 |
Expired |
GW-RS1240-16 |
12 Dec 2016 |
13 Dec 2016 to 06 Jun 2017 |
Expired |
|
GW-RS1233-16 |
12 Dec 2016 |
14 Dec 2016 to 06 Jun 2017 |
Expired |
|
GW-RS1234-16 |
12 Dec 2016 |
20 Dec 2016 to 19 Jun 2017 |
Expired |
|
Discharge License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table
3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May
2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun
2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS1297-16 |
15 Dec 2016 |
16 Dec 2016 to 14 Jun 2017 |
Expired |
GW-RS1305-16 |
22 Dec 2016 |
24 Dec 2016 to 13 Jun 2017 |
Cancelled |
|
GW-RS0289-17 |
31 Mar 2017 |
02 Apr 2017 to 02 Jul /2017 |
Valid |
|
GW-RS0314-17 |
07 Apr 2017 |
11 Apr 2017 to 04 Oct 2017 |
Valid |
|
GW-RS0338-17 |
13 Apr 2017 |
28 May 2017 to 27 Aug 2017 |
Valid |
|
GW-RS0334-17 |
18 Apr 2017 |
21 Apr 2017 to 06 Oct 2017 |
Valid |
|
GW-RS0348-17 |
18 Apr 2017 |
25 Apr 2017 to 24 Oct 2017 |
Valid |
|
GW-RS0527-17 |
16/6/2017 |
17 Jun 2017 to 20 Sep 2017 |
Valid |
|
GW-RS0535-17 |
16/6/2017 |
17 Jun 2017 to 20 Sep 2017 |
Valid |
|
Water
Discharge License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date
of
Submission |
Condition 2.7
and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov
2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan
2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15
Nov 2010 |
Permit
issued |
Valid |
Notification
of Works Under APCO |
322293 |
07
Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS1338-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
GW-RS0343-17 |
19 Apr 2017 |
21 Apr 2017 to 17 Jul 2017 |
Valid |
|
GW-RS0362-17 |
21 Apr 2017 |
30 Apr 2017 to 31 Aug 2017 |
Cancelled |
|
GW-RS0433-17 |
16 May 2017 |
18 May 2017 to 31 Aug 2017 |
Valid |
|
GW-RS0532-17 |
15 Jun 2017 |
1 Jul 2017 to 31 Dec 2017 |
Valid |
|
Discharge
Licenses |
WT00013967-2012 |
17
Sep 2012 |
30
Sep 2017 |
Cancelled |
WT00014966-2013 |
08 Jan 2013 |
31 Jan 2018 |
Cancelled |
|
WT00020725-2015 |
14
Jan 2015 |
30
Jul 2017 |
Valid |
|
WT00024255-2016 |
18
May 2016 |
31
Jan 2021 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal Ordinance
(Land) |
Account No.: 7011587 |
11
Oct 2010 |
Account approved |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date
of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.9.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Water Discharge License (Discharge
at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Valid |
WT00024951-2016 |
08 Jul 2016 |
8 Jul 2016 to 31
Dec 2017 |
Valid |
Table 3.9 Summary of submission status under
FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 Mar
2011 |
Amendment for Management
Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar
2011 |
Condition 2.8 |
Location Plan |
15 Mar
2011 |
Condition 2.9 |
Noise Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape
Plan (Rev.3) |
30 Jan 2015 |
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.10.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
24 Nov 2015 |
N/A |
Valid |
||
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10
Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24
Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21
July 2011 |
N/A |
Valid |
Construction
Noise Permits (CNP) for non-piling equipment |
GW-RS1251-16 |
07 Dec 2016 |
18 Dec 2016 to 17 Jun 2017 |
Expired |
GW-RS0238-17 |
23 Mar 2017 |
08 Apr 2017 to 07 Jun 2017 |
Cancelled |
|
GW-RS0482-17 |
02 Jun 2017 |
08 Jun 2017 to 07 Sep 2017 |
Valid |
|
GW-RS1327-16 |
29-Dec-16 |
29 Dec 2016 to 27 Jun 2017 |
Valid |
|
GW-RS0562-17 |
28-Jun-17 |
30 Jun 2017 to 27 Dec 2017 |
Valid |
|
GW-RS0552-17 |
22-Jun-17 |
28 Jun 2017 to 27 Dec 2017 |
Valid |
|
Water
Discharge License |
WT00025282-2016 |
15 Sep
2016 |
30 Sep 2021 |
Valid |
Dumping Permit (Approach Ramp) (Type
1 – Open Sea Disposal) |
EP/MD/17-078 |
01
Oct 2016 |
31
Mar 2017 |
Valid |
Table 3.11 Summary of submission status under
FEP-07/364/2009/D
EP Condition |
Submission |
Date of Submission |
Condition 2.13 |
Landscape Plan (Rev.5) |
09 December 2016 |
Condition 2.9 |
Noise Management Plan (Rev.4) |
15
February 2016 |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West
3.1.11.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-12/364/2009/D for contract no.
HK/2012/08 showed in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 Mar 2013 |
N/A |
Valid |
FEP-12/364/2009/D |
1 Aug 2016 |
N/A |
Valid |
|
FEP-06/356/2009 |
5 March 2013 |
N/A |
Valid |
|
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1336-16 |
29 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
GW-RS1371-16 |
5 Jan 2017 |
9 Jan 2017 to 08 Jul 2017 |
Valid |
|
GW-RS0098-17 |
1 Feb 2017 |
26 Feb 2017 to 25 Aug 2017 |
Valid |
|
Water Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Cancelled |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Table
3.13 Summary
of submission status under FEP-12/364/2009/D
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management Plan (Rev.2) |
9 July 2013 |
Condition 2.14 |
Landscape Plan (Rev.4) |
24 August 2015 |
Contract
no. HY/2010/08 –Central – Wanchai Bypass Tunnel – Tunnel (Slip Road 8)
3.1.12.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-10/364/2009/B for contract no.
HK/2012/08 showed in Table 3.14 and Table 3.15.
Table
3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-10/364/2009/B |
26
Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26
Jul 2013 |
NA |
Valid |
|
Notification of Works Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing Account under Waste Disposal Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge
License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Cancelled |
WT00020468-2014 |
2014-12-03 |
2018-07-31 |
Valid |
|
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1254-16 |
10 Dec 2016 |
10 Dec 2016 to 07 Jun 2017 |
Expired |
GW-RS0086-17 |
31 Jan 2017 |
31 Jan 2017 to 30 Jul 2017 |
Valid |
|
GW-RS0092-17 |
31 Jan 2017 |
31 Jan 2017 to 31 Jul 2017 |
Valid |
|
GW-RS0290-17 |
08 Apr 2017 |
08 Apr 2017 to 30 Sep 2017 |
Valid |
|
GW-RS1366-16 |
06 Jan 2017 |
06 Jan 2017 to 26 Jun 2017 |
Expired |
|
GW-RS0201-17 |
18 Mar 2017 |
18 Mar 2017 to 17 Sep 2017 |
Cancelled |
|
GW-RS0347-17 |
27 Apr 2017 |
27 Apr 2017 to 18 Oct 2017 |
Valid |
|
GW-RS0360-17 |
20 Apr 2017 |
20 Apr 2017 to 19 Oct 2017 |
Cancelled |
|
GW-RS0368-17 |
19 Apr 2017 |
21 Apr 2017 to 18 Oct 2017 |
Valid |
|
GW-RS0499-17 |
08 Jun 2017 |
09 Jun 2017 to 28 Nov 2017 |
Valid |
|
GW-RS0514-17 |
13 Jun 2017 |
18 Jun 2017 to 16 Sep 2017 |
Valid |
|
GW-RS0515-17 |
13 Jun 2017 |
18 Jun 2017 to 16 Sep 2017 |
Valid |
|
GW-RS0518-17 |
13 Jun 2017 |
26 Jun 2017 to 25 Nov 2017 |
Valid |
|
GW-RW0197-17 |
19 Apr
2017 |
24 Apr 2017 to 20 Oct 2017 |
Valid |
Table
3.15 Summary
of submission status under FEP-10/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.2) |
19 May 2014 |
Condition 2.16 |
Additional Mitigation Plan (Rev.2) |
18 February 2015 |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
3.1.13.
The current status on licenses and/or permits on environmental
protection pertinent and submission under FEP-11/364/2009/E for contract no.
HY/2011/08 showed in Table 3.16 and Table 3.17.
Table
3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2011/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
N/A |
Valid |
FEP-11/364/2009/E |
22 Dec 2014 |
N/A |
Valid |
|
Notification
of Works Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
5213-121-L2837-01 |
19 Apr 2016 |
N/A |
Registered |
5213-151-L2837-02 |
24 May 2016 |
N/A |
Registered |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Registered |
|
5213-134-L2952-01 |
12 May 2017 |
N/A |
Registered |
|
Billing
Account under Waste Disposal Ordinance |
7019640 |
27 Mar 2014 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0068-17 |
24 Jan 2017 |
01 Feb 2017 to |
Cancelled |
GW-RS0260-17 |
27 Mar 2017 |
29 Mar 2017 to |
Cancelled |
|
GW-RS1151-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Expired |
|
GW-RS1168-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Expired |
|
GW-RS1178-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Expired |
|
GW-RS1134-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
GW-RS1137-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
GW-RS0100-17 |
1 Feb 2017 |
03 Feb 2017 to 31 Jul 2017 |
Valid |
|
GW-RS0139-17 |
23 Feb 2017 |
01 Mar 2017 to 31 Aug 2017 |
Valid |
|
GW-RS0146-17 |
23 Feb 2017 |
01 Mar 2017 to 31 Aug 2017 |
Valid |
|
GW-RS0294-17 |
31 Mar 2017 |
06 Apr 2017 to 30 Sep 2017 |
Valid |
|
GW-RS0359-17 |
25 Apr 2017 |
01 May 2017 to 31 Oct 2017 |
Valid |
|
GW-RS0375-17 |
25 Apr 2017 |
01 May 2017 to 31 Oct 2017 |
Valid |
|
GW-RS0381-17 |
26 Apr 2017 |
01 May 2017 to 31 Oct 2017 |
Valid |
|
GW-RS0460-17 |
18 May 2017 |
01 Jun 2017 to 31 Oct 2017 |
Valid |
|
GW-RS0463-17 |
18 May 2017 |
01 Jun 2017 to 31 Oct 2017 |
Valid |
|
GW-RS0465-17 |
18 May 2017 |
01 Jun 2017 to 31 Oct 2017 |
Valid |
|
GW-RS0523-17 |
15 Jun 2017 |
01 Jul 2017 to 31 Dec 2017 |
Valid |
|
GW-RS0528-17 |
15 Jun 2017 |
01 Jul 2017 to 31 Dec 2017 |
Valid |
|
Water Discharge Licence |
WT00020242-2014 |
04
Nov 2014 |
30
Nov 2019 |
Cancelled |
WT00022046-2015 |
15
Jul 2015 |
31
Jul 2019 |
Valid |
|
WT00022753-2015 |
22
Jun 2017 |
30
Apr 2021 |
Valid |
|
WT00024561-2016 |
30
May 2016 |
31
May 2021 |
Valid |
|
WT00025858-2016 |
17
Oct 2016 |
31
Oct 2021 |
Valid |
|
WT00026829-2017 |
14
Jun 2017 |
31
Jan 2022 |
Valid |
|
WT00027343-2017 |
01
Mar 2017 |
31
Mar 2022 |
Valid |
Table 3.17 Summary
of submission status under FEP-11/364/2009/E
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.4) |
08 November 2016 |
Condition 2.14 |
Landscape Plan (Rev.2) |
18 Feb 2015 |
Condition 2.13 a) |
Operational Air Quality Management Plan for West Ventilation Building
(Rev.0) |
25 Nov 2014 |
Condition 2.13 b) |
Operational Air Quality Management Plan for Central Ventilation
Building (Rev.0) |
03 March 2017 |
Condition 2.13 c) |
Operational Air Quality Management Plan for East Ventilation Building
and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Condition 2.13 d) |
Operational Air Quality Management Plan for an Electrostatic
Precipitator system for EVB Operation (Rev.0) |
06 April 2017 |
Condition 2.13 e) |
Operational Air Quality Management Plan for ventilation system of
Eastern Portal of the CWB Tunnel (Rev.0) |
23 October 2016 |
Noise
Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a*** |
Footbridge for Ex-Harbour Road Sports Centre |
M2b |
Noon-day
Gun Area |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
M7e* |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8** |
City Hall |
Remark *: Location ID has been updated from M7 to
M8 for City Hall
Remark **: M7e has become a reference station
starting from 7 Aug 2012
Remarks***: The location ID
of monitoring station M1a was updated as “Footbridge for Ex-Harbour Road Sports
Centre” in May 2017.
Real time Noise Monitoring
Stations
4.1.2.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Hong Kong Electric
Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee
Mo Fan Memorial School |
Tin Hau |
RTN4 |
Causeway Bay
Community Centre |
Noise
Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 - hours basis when noise
generating activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
· One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
· One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring
Equipment
4.1.7.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air quality monitoring stations for the
Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour
Grand Hotel Boundary Wall** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway
Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**:
The location ID of monitoring station CMA1b was updated as “Oil Street Site
Office” in April 2013. The location ID of monitoring station CMA1b was updated
as “Harbour Grand Hotel Boundary Wall” with respect to the fine adjustment of
monitoring station from the Oil Street Site Office to Harbour Grand Hotel
Boundary Wall from 05 June 2017 onwards due to demolition of Oil Street Site
Office.
Remarks***:
The station ID and monitoring location was updated in December 2014 with
respect to monitoring station relocation.
Air QUALITY Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
· 0.6 – 1.7 m3 per minute
adjustable flow range;
· Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
· Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
· Capable of providing a minimum exposed
area of 406 cm2;
· Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
· Equipped with a shelter to protect the
filter and sampler;
· Incorporated with an electronic mass
flow rate controller or other equivalent devices;
· Equipped with a flow recorder for
continuous monitoring;
· Provided with a peaked roof inlet;
· Incorporated with a manometer;
· Able to hold and seal the filter paper
to the sampler housing at horizontal position;
· Easily changeable filter; and
· Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement
/ Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24 hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and monitoring
stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no.
HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no. HK/2009/01
– Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai West
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB)– Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline
noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation starting from January 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.2 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for
Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
*
Remark: M7e has become a reference station starting from 7 Aug 2012
5.1.3
No action or limit level exceedance was
recorded in this reporting month.
5.1.4
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract
no HK/2009/01
and HK/2009/02
Station |
Description |
M1a |
Footbridge for Ex-Harbour Road Sports Centre |
5.1.6
Five limit level
exceedances were recorded at M1a – Footbridge for Ex-Harbour Road Sports Centre
on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting month.
5.1.7
No Construction works was conducted under
Contract HK/2009/01 around the monitoring station on 31 May 2017 and 08, 13, 22
and 26 June 2017 in the reporting month, non WDII-CWB Projects construction
works were observed on 31 May 2017 and 08, 13, 22 and 26 June 2017 during the
monitoring period as the major noise contribution. Hence, the exceedances were
considered as non-Project related.
5.1.8
Despite rebar fixing, and formwork fixing
works was conducted on 31 May 2017 and 13 and 26 June 2017 under Contract
HK/2009/02, and concreting works was conducted on 08 and 22 June 2017 under
Contact HK/2009/02, non WDII-CWB Projects construction works was observed on 31
May 2017 and 08, 13, 22 and 26 June 2017 during monitoring period and observed
as the major noise contribution. Hence, the exceedances were considered as
non-Project related.
5.1.9
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.1.10 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Stations
for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.11
No action or limit level exceedance was
recorded in this reporting month.
5.1.12
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
5.1.13 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.14
Three limit level exceedances were recorded on
08, 16 and 19 June 2017 in this reporting month.
5.1.15
Despite lifting works by crane and falsework
erection works were conducted under Contract HY/2009/19 on 08 and 19 June 2017
respectively, no construction activity was conducted on 16 June 2017 and
traffic noise was observed as the major noise contribution on 08, 16 and 19
June 2017. Hence, the exceedances were considered as non-Project related.
5.1.16
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D
5.1.17 The
commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02 September
2013. The proposed divisions of noise monitoring stations are summarized in
Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.18
No action or limit level exceedance was
recorded in this reporting month.
5.1.19
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.1.20 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2011/08 are summarized in Table 5.6 below:
Table 5.6
Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station
starting from 7 Aug 2012
5.1.21
No action or limit level exceedance was
recorded in this reporting month.
5.1.22
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013. The baseline noise level of RTN4- Causeway Bay
Community Centre has adopted the results from the baseline noise monitoring
report for EP/364/2009 in 22 April 2010 in which approved by EPD.
5.2.2.
Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up
on 4 Sep 2012 and real time noise monitoring station RTN3 set up was performed
on 14 Sep 2012. Real time noise baseline capturing was conducted during time
period without construction work from 21 Sep 2012 to 04 Oct 2012. Real time noise monitoring at RTN3 – Po Leung Kuk Yu Lee Mo Fan Memorial School was
commenced since 06 Oct 2012.
5.2.3.
Real-time noise monitoring station RTN2 previously located at oil Street
Community Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct
2012, which is a representative of the noise sensitive receiver City Garden.
The baseline noise level of RTN2a will adopt the results derived from the
baseline noise monitoring conducted at Hong Kong Electric Centre from 4
December 2009 to 17 December 2009.
5.2.4.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
5.2.5.
With respect to the non-CWB Project building construction at Oil Street,
the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was
finely adjusted from Northeast Side to Northwestern side at Roof Top location
on 03 March 2017.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.2.6.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 5.7 Real
Time Noise
Monitoring Stations for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu Lee Mo Fan Memorial School |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during restrict
hours and night time period are for information only and noise during CNP
period shall be controlled under NCO.
5.2.7.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded during daytime on 21 June 2017 in the reporting month. After checking
with Contractor of HY/2009/19, no construction works was conducted on 21 June
2017 during the monitoring period while adverse weather condition was recorded
during the monitoring period and considered as the major noise contribution.
Hence, the exceedances were considered as non-Project related.
5.2.8.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded during daytime on 21 June 2017 in
the reporting month. After checking with Contractor of HY/2009/19, no
construction works was conducted on 21 June 2017 during the monitoring period
while adverse weather condition was recorded during the monitoring period and
considered as the major noise contribution. Hence, the exceedances were
considered as non-Project related.
5.2.9.
Limit level exceedances were recorded at
RTN3- Yu Lee Mo Fan Memorial School was recorded during daytime on 13 and 21
June 2017 in the reporting month. After checking with Contractor of HY/2009/19,
despite erection of U-beam structure was conducted on 13 June 2017, no major
noise concern was considered and no construction works was conducted on 21 June
2017 during the monitoring period while adverse weather condition was recorded
during the monitoring period on 13 and 21 June 2017 and considered as the major
noise contribution. Hence, the exceedances were considered as non-Project
related.
5.2.10.
No limit level exceedance
was recorded at RTN4- Causeway Bay Community Centre was recorded in the
reporting month.
5.2.11.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08 – Central - Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning
5.2.12.
The proposed division of noise monitoring
stations are summarized in Table 5.8 below. Real time noise monitoring
for major construction works under contract no. HY/2011/08 was commenced on 19
March 2015.
Table 5.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location
ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN4 |
Tin Hau |
Causeway
Bay Community Centre |
* Real time noise monitoring results and
graphical presentation during restrict hours and night time period are for
information only and noise during CNP period shall be controlled under NCO.
5.2.13.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded during daytime on 21 June 2017 in the reporting month. After checking
with Contractor of HY/2011/08, no construction works was conducted on 21 June
2017 during the monitoring period while adverse weather condition was recorded
during the monitoring period and considered as the major noise contribution.
Hence, the exceedances were considered as non-Project related.
5.2.14.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded during daytime on 21 June 2017 in
the reporting month. After checking with Contractor of HY/2011/08, no
construction works was conducted on 21 June 2017 during the monitoring period
while adverse weather condition was recorded during the monitoring period and
considered as the major noise contribution. Hence, the exceedances were
considered as non-Project related.
5.2.15.
No limit level exceedance
was recorded at RTN4- Causeway Bay Community Centre were recorded in the
reporting month.
Contract no. HY/2009/18 –
Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.1
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.9 below.
Table 5.9 Air Quality Monitoring Stations for Contract
no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
5.3.2
No exceedance was recorded in the reporting
month.
5.3.3
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.3.4
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality
monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Quality Monitoring Station for Contract
no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.5
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting month.
5.3.6
After checking with the Contractor of
HK/2009/01, no construction works was undertaken around the monitoring location
on the monitoring date under Contractor of HK/2009/01 and no particular
observation regarding air quality impact was observed during sampling while sweeping
works conducted directly at the monitoring station by Pedestrian Plaza
management office could potentially contribute to the elevated particulates
level in the vicinity of the monitoring equipment. Hence, the exceedance is
considered as not related to the Project.
5.3.7
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.8
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air quality monitoring stations are summarized in Table 5.11
below.
Table 5.11 Air Quality Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.9
No exceedance was recorded in the reporting
month.
5.3.10
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.3.11
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.12 below.
Table 5.12
Air
Quality Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.12
No exceedance was recorded in the reporting
month.
5.3.13
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.3.14
The proposed division of air quality monitoring
stations are summarized in Table 5.13 below. Air quality monitoring
for the tunnel works under contract no. HY/2009/19 was commenced on 26 April
2011.
Table 5.13 Air Quality
Monitoring
Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Harbour Grand Hotel Boundary Wall |
CMA2a |
Causeway Bay Community Centre |
5.3.15
One 1hr TSP limit level exceedance was
recorded at CMA1b – Harbour Grand Hotel Boundary Wall on 03 June 2017 in the
reporting month.
5.3.16
No construction works was undertaken around
the monitoring location on the monitoring date under Contractor of HY/2009/19
and no particular observation regarding air quality impact was observed during
sampling and dust mitigation measure including haul road and dusty surface maintained
in dampened condition were generally implemented. The exceedance was considered
to be non-project related and potentially contributed by localized ambient
condition and other environmental factor.
5.3.17
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
5.3.18
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/B was on May 2014. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.14 below.
Table 5.14
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.19
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting month.
5.3.20
After checking with the Contractor of
HK/2012/08, despite manhole installation was undertaken around the monitoring
location on the monitoring date under Contractor of HK/2012/08 and no
particular observation regarding air quality impact was observed during
sampling while sweeping works conducted directly at the monitoring station by
Pedestrian Plaza management office could potentially contribute to the elevated
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
5.3.21
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D
5.3.22
The commencement of construction works for
Contract no. HY/2010/08 under FEP-12/364/2009/D was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.15 below.
Table 5.15
Air
Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.23
No exceedance was recorded in the reporting
month.
5.3.24
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.3.25
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.16 below.
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
CMA1b |
Harbour Grand Hotel Boundary Wall |
CMA2a |
Causeway Bay Community Centre |
CMA5b |
Pedestrian Plaza |
5.3.26
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting month.
5.3.27
After checking with the Contractor of
HY/2011/08, rebar and formwork fixing works was undertaken around the
monitoring location on the monitoring date under Contractor of HY/2011/08 and
no particular observation regarding air quality impact was observed during
sampling while sweeping works conducted directly at the monitoring station by
Pedestrian Plaza management office could potentially contribute to the elevated
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
5.3.28
One 1hr TSP limit level exceedance was
recorded at CMA1b – Harbour Grand Hotel Boundary Wall on 03 June 2017 in the
reporting month.
5.3.29
After checking with the Contractor of
HY/2011/08, rebar and formwork fixing works was undertaken around the
monitoring location on the monitoring date under Contractor of HY/2011/08 and
no particular observation regarding air quality impact was observed during
sampling and dust mitigation measure including hard paving of haul road were
generally implemented. The exceedance was considered to be non-project related
and potentially contributed by localized ambient condition and other
environmental factor.
5.3.30
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.4.1.
Inert C&D wastes and non-inert C&D wastes were disposed in this
reporting month. Details of the waste flow table are summarized in
Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed, m3 |
4.465 |
107988.315 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
Nil |
98512.03 |
N/A |
Non-inert C&D materials disposed, m3 |
12.74 |
5291.8 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
Nil |
1285746 |
N/A |
Chemical waste disposed, kg |
Nil |
10400 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) , m3 |
Nil |
11527 |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 |
Nil |
16261 |
East of Cha Chau South Brothers |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
38 |
522204.412 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D materials disposed, m3 |
64 |
4480.317 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
17718 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
Nil |
65663 |
South Cheung Chau |
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
102.54 |
1415385.29 |
||
Nil |
58787.05 |
||
19.19 |
4385.81 |
||
Nil |
878.37 |
||
Nil |
6772 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for
Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
Nil Nil |
625200.92 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT HY/2010/08 |
Non-inert C&D
materials disposed, m3 |
Nil Nil |
4673.91 1.58 |
SENT Landfill WENT Landfill |
Non-inert C&D
materials recycled, m3 |
Nil |
5496446.2 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21
Details of Waste Disposal for
Contract no. HY/2009/19
Inert
C&D materials disposed, ton |
3472.09 |
690466.01 |
TM38 |
Inert
C&D materials recycled, ton |
Nil |
82349.7 |
N/A |
Non-inert
C&D materials disposed, ton |
105.42 |
5988.31 |
SENT Landfill |
Non-inert
C&D materials recycled, ton |
Nil |
565.63 |
N/A |
Chemical
waste disposed, kg |
Nil |
10.15 |
N/A |
Marine
Sediment (Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine
Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 –
Confined Marine Disposal), m3 |
Nil |
30751 |
East of Sha Chau |
Contract no. HK/2012/08 Wan Chai
Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Table
5.22 Details of Waste Disposal for Contract
no. HK/2012/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
112 Nil |
183190 116668 |
TKO 137 TM38 |
Inert
C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert
C&D materials disposed, m3 |
180 |
7817 |
SENT |
Non-inert
C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical
waste disposed, kg |
Nil |
Nil |
N/A |
Marine
sediment (Type 1) disposal, m3 |
Nil |
3145 |
South of Cheung Chau / East of Sha Chau / South
of The Brothers |
Remarks: The quantity of inert C&D material disposed, recycled,
non-inert C&D material disposed, recycled are reported up to calendar month
of May 2017. The cumulative amount of inert C&D material disposed is
clarified in the June 2017 reporting month.
Contract no. HY/2010/08
Central
– Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
Nil Nil Nil 18.37 |
583935.84 262656.6 82911.8 72688.52 |
TM 38 WENT SENT TKO area 137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
372.76 |
4915.79 |
SENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
1431 |
N/A |
Type 1 – Open Sea Disposal, m3 |
Nil |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined Marine disposal, m3 |
Nil |
549.2 |
East Sha Chau |
Table 5.23
Details
of Waste Disposal for Contract no. HY/2010/08
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
5.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.24.
Table
5.24 Details of Waste Disposal for
Contract no. HY/2011/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
52.89 |
734.19 |
CWPF & TKO137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
281.91 |
2907.96 |
SENT |
Non-inert C&D materials recycled, ton |
Nil |
31.72 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
6.1.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention Exhibition Centre
– Tunnel Works under FEP-02/364/2009
6.1.2.
Five limit level exceedances were recorded at
M1a – Footbridge for Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13,
22 and 26 June 2017 in the reporting month.
6.1.3.
No construction works was conducted under
Contract HK/2009/01 around the monitoring station on 31 May 2017 and 08, 13, 22
and 26 June 2017 in the reporting month, non WDII-CWB Projects construction
works were observed on 31 May 2017 and 08, 13, 22 and 26 June 2017 during the
monitoring period as the major noise contribution. Hence, the exceedances were
considered as non-Project related.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4.
Five limit level exceedances were recorded at
M1a – Footbridge for Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13,
22 and 26 June 2017 in the reporting month.
6.1.5.
Despite rebar fixing, and formwork fixing
works was conducted on 31 May 2017 and 13 and 26 June 2017 under Contract
HK/2009/02, and concreting works was conducted on 08 and 22 June 2017 under
Contact HK/2009/02, non WDII-CWB Projects construction works was observed on 31
May 2017 and 08, 13, 22 and 26 June 2017 during monitoring period and observed
as the major noise contribution. Hence, the exceedances were considered as
non-Project related.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.6.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.7.
Three limit level exceedances were recorded
on 08, 16 and 19 June 2017 in this reporting month.
6.1.8.
Despite lifting works by crane and falsework
erection works were conducted under Contract HY/2009/19 on 08 and 19 June 2017
respectively, no construction activity was conducted on 16 June 2017 and
traffic noise was observed as the major noise contribution on 08, 16 and 19
June 2017. Hence, the exceedances were considered as non-Project related.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.9.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
6.1.10.
No exceedance was recorded in the reporting
month.
Real Time Noise Monitoring
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.11.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot was recorded in the
reporting month.
6.1.12.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded on 24 May 2017 during daytime in
the reporting month. After checking
with Contractor of HY/2009/19, despite sheet piling works was conducted during
the monitoring period, adverse weather condition under Red Rainstorm Warning
Signal was considered as the major noise contribution during monitoring and
hence the exceedance was concluded as non-Project related.
6.1.13.
Limit level exceedances were recorded at
RTN3- Yu Lee Mo Fan Memorial School was recorded during daytime on 13 and 21
June 2017 in the reporting month. After checking with Contractor of HY/2009/19,
despite erection of U-beam structure was conducted on 13 June 2017, no major
noise concern was considered and no construction works was conducted on 21 June
2017 during the monitoring period while adverse weather condition was recorded
during the monitoring period on 13 and 21 June 2017 and considered as the major
noise contribution. Hence, the exceedances were considered as non-Project
related.
6.1.14.
No limit level exceedance was recorded at
RTN4- Causeway Bay Community Centre was recorded in the reporting month.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
6.1.16.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded during daytime on 21 June 2017 in
the reporting month. After checking with Contractor of HY/2011/08, no
construction works was conducted on 21 June 2017 during the monitoring period
while adverse weather condition was recorded during the monitoring period and
considered as the major noise contribution. Hence, the exceedances were
considered as non-Project related.
6.1.17.
No limit level exceedance was recorded at
RTN4- Causeway Bay Community Centre were recorded in the reporting month.
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre – Tunnel Works under FEP-02/364/2009
6.2.2.
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting month.
6.2.3.
After checking with the Contractor of
HK/2009/01, no construction works was undertaken around the monitoring location
on the monitoring date under Contractor of HK/2009/01 and no particular
observation regarding air quality impact was observed during sampling while sweeping
works conducted directly at the monitoring station by Pedestrian Plaza
management office could potentially contribute to the elevated particulates
level in the vicinity of the monitoring equipment. Hence, the exceedance is
considered as not related to the Project.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
6.2.5.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.2.6.
One 1hr TSP limit level exceedance was
recorded at CMA1b – Harbour Grand Hotel Boundary Wall on 03 June 2017 in the
reporting month.
6.2.7.
No construction works was undertaken around
the monitoring location on the monitoring date under Contractor of HY/2009/19
and no particular observation regarding air quality impact was observed during
sampling and dust mitigation measure including haul road and dusty surface
maintained in dampened condition were generally implemented. The exceedance was
considered to be non-project related and potentially contributed by localized
ambient condition and other environmental factor.
Contract no. HK/2012/08 Wan Chai Development Phase
II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
6.2.8.
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting month.
6.2.9.
After checking with the Contractor of
HK/2012/08, despite manhole installation was undertaken around the monitoring
location on the monitoring date under Contractor of HK/2012/08 and no
particular observation regarding air quality impact was observed during
sampling while sweeping works conducted directly at the monitoring station by
Pedestrian Plaza management office could potentially contribute to the elevated
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.2.10.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08
Central
–Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
6.2.12.
After checking with the Contractor of
HY/2011/08, rebar and formwork fixing works was undertaken around the
monitoring location on the monitoring date under Contractor of HY/2011/08 and
no particular observation regarding air quality impact was observed during
sampling while sweeping works conducted directly at the monitoring station by
Pedestrian Plaza management office could potentially contribute to the elevated
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
6.2.13.
One 1hr TSP limit level exceedance was
recorded at CMA1b – Harbour Grand Hotel Boundary Wall on 03 June 2017 in the
reporting month.
6.2.14.
After checking with the Contractor of
HY/2011/08, rebar and formwork fixing works was undertaken around the
monitoring location on the monitoring date under Contractor of HY/2011/08 and
no particular observation regarding air quality impact was observed during
sampling and dust mitigation measure including hard paving of haul road were
generally implemented. The exceedance was considered to be non-project related
and potentially contributed by localized ambient condition and other
environmental factor.
6.4.1
No particular action taken was taken for site
audits since no non-compliance was recorded in the reporting period.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/E, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area include road and drain works, backfilling works and reinstatement of
Culvert and Cooling mains and installation of irrigation piping at P1 road were
performed in June 2017 reporting month. As no project
related exceedance were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4.
According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activities under Wan Chai Development Phase II were, road and drains
construction, tunnel construction and backfilling works at Wan Chai West and
Wan Chai East. The major construction activities under Central-Wan Chai Bypass
and Island Eastern Corridor Link Projects were drainage works and ventilation
building construction at Central; temporary reclamation removal works at
Causeway Bay, road works and side wall construction at Victoria Park; bridge
construction, piling works, foundation works and building construction at North
Point area in the reporting month. In addition, other non-Wan Chai Development
Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan Chai North and North
Point area.
7.0.5.
As relevant site mitigation measures for air
quality and construction noise were implemented, no significant air quality impact
and noise impact from construction activities was concluded in the reporting
month. Besides, no project related exceedance was recorded during the air quality
and noise environmental monitoring events in the reporting month. Thus, it is
evaluated that the cumulative construction impact from the concurrent projects
including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II
(WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects
(IECL) was insignificant.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08.
No non-conformance was identified during the site audits. The Contractors rectified major
observations and recommendations made during the audit sessions.
8.0.2.
Site inspections for Contract no. HY/2009/15
were carried out during this reporting period. No observation
was found in the reporting month.
Table 8.3 Summary of Environmental Inspections for Contract
no. HY/2009/19
Item |
Date |
Observations |
Action
taken by Contractor |
Completion
date |
170607_1 |
7 Jun 2017 |
Watering shall be provided more frequently to
haul road to avoid dust emission (Portion 3) |
Watering was provided to haul road to avoid
dust emission |
Completion as observed on 14 June 2017 |
170607_2 |
7 Jun 2017 |
The contractor shall properly follow-up with
the provision / arrangement for movable noise barrier (Opposite to Habour
Grand Hotel) |
Contractor provide relevant information for
further review and comment |
Completion as observed on 21 June 2017 |
170614_1 |
14 Jun 2017 |
Contractor shall critically review the
operation and treatment capacity of water treatment unit to ensure the
discharge quality (Watson Road) |
Additional water treatment unit was deployed |
Completion as observed on 28 June 2017 |
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
170615_01 |
15 Jun
2017 |
Drip tray
shall be provided for oil and chemical containers at Portion 3&4. |
The oil
and chemical containers were removed on site. |
Completion
as observed on 20 June 2017 |
170620_01 |
20 Jun
2017 |
Chemical
containers at Portion 5 shall be provided with proper labelling and stored
properly at appropriate storage area. |
Chemical
containers were removed on site. |
Completion
as observed on 29 July 2017. |
Table 8.6 Summary
of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
170606_01 |
6-Jun-17 |
Water
spraying shall be implemented on dusty ground surface for dust suppression at
Zone A2 |
Water
spraying has implemented and the ground was observed wet. |
Completion
as observed on 13 June 2017 |
170613_01 |
13-Jun-17 |
Bunding
shall be provided along the culvert L structure alignment to prevent
potential surface runoff from site. |
Bunding
was provided at the concerned location. |
Completion
as observed on 20 June 2017 |
Table 8.7 Summary
of Environmental Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
170531_1 |
31 May
2017 |
Impermeable
barrier shall be tighten and deployed the extension to the seabed (TS3 South West) |
Impermeable
barrier was tighten and deployed the extension to the seabed |
Completion
as observed on 9 June 2017 |
170609_1 |
09 Jun
2017 |
Impermeable
barrier shall be deploy and enclose the underwater excavation (-4 to
-7mPD) to avoid potential contamination to nearby water (TS3 South
West) |
Impermeable
barrier was deployed to enclose the underwater excavation area |
Completion
as observed on 14 June 2017 |
170614_1 |
14 Jun
2017 |
Damaged
embankment shall be repair to avoid surface runoff (TS3) |
Damaged
embankment was repaired to avoid surface runoff |
Completion
as observed on 21 June 2017 |
170621_1 |
21 Jun
2017 |
Silt
curtain shall be tighten and enclose the seawall block lifting works to avoid
muddy dispersion (TS3) |
No further
seawall lifting works was observed |
Completion
as observed on 28 June 2017 |
170621_2 |
21
Jun 2017 |
Piping
shall be disconnect and ensure the discharge follow the discharge license
condition (TS3) |
The
concerned piping was disconnected |
Completion
as observed on 28 June 2017 |
9.0.1.
No environmental complaints were received in the reporting month.
9.0.2.
No Notification of Summons and Successful Prosecutions was received in
the reporting month.
9.0.3.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.4. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
June 2017 |
0 |
September 2010 – May 2017 |
80 |
Total |
80 |
Table
9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
1 |
0 |
1 |
Noise |
1 |
0 |
1 |
Water |
0 |
0 |
0 |
Waste |
0 |
0 |
0 |
Total |
2 |
0 |
2 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be commenced in
Coming Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/15 |
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE
and TPCWAW ·
Reinstatement work at the PRE Office car park area ·
Re-surfacing work at Hung Hing Road |
·
Dust control during dust generating activities and covering for
stockpile stored on site. ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the nearby water. ·
Maintain regular cleaning of floating refuses within construction
area. |
HY/2009/18 |
·
Drainage works ·
Road works ·
Landscaping works ·
Maintenance works |
·
Dust control during dust generating activities ·
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2009/19 |
·
Approach ramp sheet piling, pre-bored piling and top soil removal works ·
Bridge Construction ·
Pier 30-32 Cap Construction ·
IEC noise enclosure/barrier installation ·
Excavation / Construction of retaining wall ·
FEHD Metal Roof Construction ·
Bridge E Permanent Parapet Construction at TB ·
Pre-bored H-piles for Approach Ramp Phase 2 Construction ·
Hing Fat Street modification works ·
Oil Street drainage works ·
Installation of skin parapet on TB bridge |
·
Noise level shall be controlled by reducing the breaking operation
rate. ·
Noise barrier shall be implemented ·
Dust control during dust generating works ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. |
HK/2009/01 |
·
Reinstatement of amenity area ·
Road and Drain works |
·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ·
Dust control during dust generating works ·
Noise mitigation measures during breaking works |
HK/2009/02 |
·
Reprovisioned Salt Water Pumping Station ·
Removal works of the existing sheet piles at the north face of WSD
Salt Water Pumping Station ·
Reprovisioned Wan Chai Ferry Pier; ·
Rectification works for the defects for the end of maintenance period
of Observation Deck and Staircase ST-01. ·
Rectification works for cracks/joints with water leakage inside OHVD
cells ·
Formwork, rebar fixing and concreting of HHR Flyover Approach Ramp. ·
Remedial works of tunnel wall, base slab and OHVD inside tunnel. ·
Remedial works for cross road ducts inside tunnel. ·
General cleaning and rectification works of OHVD, tunnel base slab,
carrier drain, cross road duct and manhole gully. ·
Rebar fixing and concreting of top slab. ·
Dismantling of scaffolding. ·
Crack mapping and remedial works to the tunnel structure. ·
Installation of waterproofing membranes at top slab. |
·
Dust control during dust generating works ·
Proper maintenance boundary surface runoff protection and water
treatment facilities to avoid potential runoff related impact. ·
Provision of protection measures to ensure no runoff out of site area
or direct discharge into public drainage system. |
HK/2012/08 |
·
Grouting ·
Construction of Slip Road 1 ·
Construction of drainage |
·
Dust control during dust generating works ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system. |
HY/2010/08 |
·
Tree protection works next to existing BGO, ·
Drainage improvement works, ·
Utility diversion works, ·
Retaining wall works ·
ELS works, ·
Construction works for subway extension |
·
Dust control during dust generating works and stockpile stored on
site. ·
Appropriate measures should be taken to ensure adequate protections
are provided for trees being transplanted and retained on site. ·
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2011/08 |
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building,
West Ventilation Building ·
Construction of Tunnel Thermal Barrier ·
Installation of Electricals and Mechanicals ·
Installation of Tunnel Features |
·
Dust control during dust generating works |
10.0.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.
10.0.5.
The construction works of Contract HK/2010/06
was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3
October 2014.